Bushveld Minerals Limited (“Bushveld Minerals” “Bushveld” Or The “Company”) Q1 2022 Operational Update
Group |
Unit |
Q1 2022 |
Q1 2021 |
Q4 2021 |
Q1 2022 vs Q1 2021 |
Q1 2022 vs Q4 2021 |
Production |
mtV1 |
972 |
688 |
962 |
41.3% |
1.0% |
Sales |
mtV1 |
8572 |
788 |
880 |
8.8% |
-2.6% |
Description |
Unit |
Q1 2022 |
Q1 2021 |
Q4 2021 |
Q1 2022 vs Q1 2021 |
Q1 2022 vs Q4 2021 |
Ore mined |
Tonnes |
425 834 |
314,573 |
347,439 |
35.4% |
22.6% |
Total mined (ore + waste) |
Tonnes |
882 024 |
617,113 |
630,475 |
42.9% |
39.9% |
Ore grade (in whole rock) |
% V2O5 |
0.80 |
0.62 |
0.87 |
29.0% |
-8.1% |
Concentrate produced |
Tonnes |
99 559 |
77,459 |
105,753 |
28.5% |
-5.9% |
Concentrate grade |
% V |
1.05 |
1.04 |
1.08 |
1.0% |
-2.8% |
Recovery from Kiln to MVO |
% |
71.3 |
74.3 |
72.7 |
-4.0% |
-1.8% |
Production (Nitrovan, FeV) |
mtV2 |
749 |
395 |
700 |
89.6% |
7.0% |
Production cash cost (C1)3 |
ZAR/KgV |
337.0 |
396.1 |
353.4 |
-14.9% |
-4.6% |
Production cash cost (C1)3 |
US$/KgV |
22.1 |
26.5 |
22.9 |
-16.6% |
-3.5% |
Foreign exchange rate |
ZAR: USD |
15.2 |
14.9 |
15.4 |
1.9% |
-1.3% |
Description |
Unit |
Q1 2022 |
Q1 2021 |
Q4 2021 |
Q1 2022 vs Q1 2021 |
Q1 2022 vs Q4 2021 |
Ore milled |
Tonnes |
45,771 |
47 305 |
45,297 |
-3.2% |
1.0% |
Ore Grade (in Whole Rock) |
% V2O5 |
1.35 |
1.38 |
1.53 |
-2.2% |
-11.8% |
Milled ore to kiln |
Tonnes |
33,381 |
32,912 |
35,551 |
1.4% |
-6.1% |
Milled Ore Grade |
% V |
0.97 |
0.94 |
0.90 |
3.2% |
7.8% |
Vametco concentrate to kiln |
Tonnes |
5,461 |
5,233 |
2,632 |
4.4% |
107.5% |
Concentrate Grade |
% V |
0.95 |
1.06 |
1.06 |
-10.4% |
-10.4% |
Recovery: Kiln to Final Product |
% |
60.6 |
81.1 |
73.4 |
-25.3% |
-17.4% |
Chemicals |
mtV2 |
36- |
– |
9 |
– |
300.0% |
Flake |
mtV2 |
7 |
132 |
26 |
-94.7% |
73.1% |
FeV |
mtV2 |
181 |
45 |
204 |
302.2% |
-11.3% |
Nitrovan |
mtV2 |
– |
116 |
23 |
-100.0% |
-100.0% |
Total production |
mtV2 |
224 |
293 |
262 |
-23.5% |
-14.5% |
Weighted average production cash cost (C1)3 |
ZAR/kgV |
587.7 |
459.1 |
567.3 |
28.0% |
3.6% |
Weighted average production cash cost (C1)3 |
US$/kgV |
38.6 |
30.7 |
36.8 |
25.7% |
4.9% |
Foreign exchange rate |
ZAR:USD |
15.2 |
14.9 |
15.4 |
1.9% |
-1.3% |